Structural works form the core phase of the Sri Hartamas Sewage Plant Redevelopment project, involving the construction of reinforced concrete structures and essential load-bearing components that support the overall facility.
Activities under this work package typically include:
Formwork installation for walls, beams, foundations and structural slabs.
Rebar fixing in accordance with design specifications to ensure adequate tensile strength.
Concrete casting operations are carried out under controlled conditions to maintain structural integrity.
Curing and surface finishing, ensuring the concrete achieves the required strength and durability.
Verification of structural alignment, dimensions and quality through routine inspections and engineer approvals.
These structural activities establish the permanent framework of the facility and ensure long-term stability and resilience in accordance with engineering standards.






Aeration Tank (Slab) Structural Works
October 2025










November 2025






Fixing Rebar for Slab Panel 22 23 (Aeration Lane 1)
December 2025
Aeration Tank Structural Works (Slab & 1st Lift Wall)








January 2026
Aeration Tank Structural Works (Slab & 1st Lift Wall)












February 2026
Aeration Tank Structural Works (Slab Panel 23)












March 2026
Aeration Tank Structural Works (Slab Panel 23)








Aeration Tank (Wall) Structural Works
November 2025














December 2025








January 2026












February 2026








March 2026
















Contiguous Bored Pile Work
November 2025










December 2025




January 2026












February 2026










March 2026








Inlet Buffer Tank Structural Work (Base Slab & 1st Lift Wall)
January 2026






February 2026














March 2026